Mitsubishi to beef up MRJ fuselage and wings

Download: Printable PDF Date: 30 Dec 2015 07:14 (UTC) category:
Publisher:
Mitsubishi to beef up MRJ fuselage and wings - Manufacturer publisher
Tatjana Obrazcova
Country: Japan Aircraft: Airplanes
Source: Flightglobal

Mitsubishi Aircraft will strengthen the MRJ regional jet’s airframe and upgrade its software, following an announcement last week about a year-long delay to the aircraft’s delivery schedule.

The Japanese manufacturer tells Flightglobal that it has scheduled two months to strengthen the aircraft’s airframe, as well as upgrade the software for its avionics, flight control system and engine control unit. Data gleaned from static strength tests prompted the modifications.

Part of the work includes strengthening the jet’s wings. When “ultimate weight loads exceeding normal loads” were exerted on some components during static strength tests, it became clear which components lacked sufficient strength, says Mitsubishi.

“Also, we are strengthening the fuselage after test feedback. We have been reinforcing these components, as planned after first flight. This kind of reinforcement work is something that happens in development work,” it adds.

The airframer says the aircraft's landing gear had no bearing on the schedule changes, but this system may be upgraded in order to have a “better-integrated aircraft”.

At a press conference last week, Mitsubishi executives had said that the airframer’s initial expectations were “too optimistic”.

In April, when it announced a push back of the regional jet’s first flight, Mitsubishi insisted that the flight delay will not impact deliveries initially scheduled for the second quarter of 2017. The programme’s prototype took its maiden sortie on 11 November.

Additional test items and changes in plan “became necessary” as it moved forward in collaboration with specialists in the USA – where it has engineering facilities – prior to the first flight and after reviewing data from the flight.

“This increased the scale of the project as a whole,” it says.

Asked how it will seek to retain customer confidence after several rounds of delays, the airframer says all risks that it is aware of have been factored in at this point.

“In preparation for some unforeseeable eventuality, we will do our utmost to advance the scheduling of each work operation to create a scheduling buffer, just in case.”

The schedule slip however means that the MRJ will be delivered in the same year as its strongest competitor, the Embraer E-Jet E2, losing the advantage of an earlier service entry.





Recommended

Embraer signs service & support agreement to enhance operational availability of Brazilian Air Force’s KC-390 fleet

Embraer signed a new long-term agreement with the Brazilian Air Force to provide support solutions for its KC-390 Millennium fleet. The agreement strengthens the partnership between Embraer and t...

Tecnam appoints Altair Solutions as Official Maintenance, Training and Certified Pre-Owned Partner

Tecnam announced the appointment of Altair Solutions as its Official Maintenance, Training and Certified Pre-Owned Partner, reinforcing its long-standing commitment to customer excellence an...

High Flying Hangars breaks ground on multi-acre development at Frederick Municipal Airport in Maryland

High Flying Hangars celebrated the groundbreaking event at its development now in progress at the Frederick Municipal Airport in Maryland (KFDK). Frederick City Mayor Michael O’Connor; Airport M...

ProLogium and Elysian Aircraft BV sign MoU to advance the vision of zero-emission aviation

ProLogium announced the signing of a MoU with Elysian Aircraft BV, a Dutch aerospace company developing large-scale battery electric aircraft and core electrification technologies for aviation. U...

Android Apps development in Riga, Latvia