50 SKY SHADES - World aviation news

Sikorsky CH-53K programme puts gearbox issues behind it

Download: Printable PDF Date: 13 Apr 2016 04:05 (UTC) category:
Publisher:
Sikorsky CH-53K programme puts gearbox issues behind it - Manufacturer publisher
Tatjana Obrazcova
Country: United States Aircraft: Helicopters
Source: Flightglobal

US Naval Air Systems Command (NAVAIR) appears to be confident that the Sikorsky CH-53K programme has put the gearbox failures and parts delays experienced prior to first flight in October 2015 behind it, but the Lockheed Martin-owned helicopter manufacturer won’t receive bonus cheques for lateness.

The US Government Accountability Office (GAO) recently stated that the King Stallion’s planned entry into low-rate production has been delayed eight months to February 2017 because of technical difficulties.

The aircraft is being developed for the US Marine Corps to replace the heavy-lift CH-53E, and should be ready for duty in 2019.

Although the US government bears the ultimate cost of delays and overruns, NAVAIR says schedule incentives were part of the arrangement “and Sikorsky was impacted due to schedule slides”.

The latest development cost estimate stands at $6.8 billion, $2 billion more than originally imagined.

Asset Image

Sikorsky/Lockheed Martin

The super-heavy-lift helicopter’s two critical technologies are the split torque gearbox and seven anhedral swept-tip composite main rotor blades and both are now flying on the first two engineering design model (EDM) aircraft. However, problems reported with the main gear box did set back the overall test schedule by delaying first flight.

“The redesigned components are flying in the test aircraft and are performing well,” confirms NAVAIR in an email to Flightglobal. “The redesigned components are flying in both test assets currently flying, and no further changes are anticipated. There has been no impact to the flight schedule because the changes were made prior to first flight.”

The programme has also been working with unnamed suppliers to “find efficiencies” and all redesigned components were ground testing prior to retrofit and flight on EDM-1. NAVAIR expects the third and fourth aircraft to join the test campaign “before the end of summer 2016”.





Recommended

Bombardier to showcase its exquisite Challenger 3500 at LABACE 2026 as part of extensive multi-city Latin American tour

Bombardier Challenger 3500 will be on display at LABACE 2026 at Campo de Marte Airport in São Paulo, revealing its impressive design and performance attributes for clients in region.&...

Avelo reaches 10 million customer milestone, reflecting strong demand for affordable and convenient travel

Avelo Airlines reached a major milestone, flying its 10 millionth Customer just five years after redefining affordable air travel in as America's most convenient airline. Since launching on April...

Groundbreaking for new facility at Clark International Airport

Lufthansa Technik Philippines, the joint venture between Lufthansa Technik and MacroAsia Corporation, broke ground this Thursday on its new base maintenance facility at Clark International Airport. Th...

Liebherr-Aerospace Technology (Shanghai) celebrates groundbreaking

The groundbreaking event of Liebherr-Aerospace Technology (Shanghai) is a milestone that marks a significant step for Liebherr – one of the world's top three landing gear suppliers with deca...

Android Apps development in Riga, Latvia