Sikorsky CH-53K programme puts gearbox issues behind it

Download: Printable PDF Date: 13 Apr 2016 04:05 (UTC) category:
Publisher:
Sikorsky CH-53K programme puts gearbox issues behind it - Manufacturer publisher
Tatjana Obrazcova
Country: United States Aircraft: Helicopters
Source: Flightglobal

US Naval Air Systems Command (NAVAIR) appears to be confident that the Sikorsky CH-53K programme has put the gearbox failures and parts delays experienced prior to first flight in October 2015 behind it, but the Lockheed Martin-owned helicopter manufacturer won’t receive bonus cheques for lateness.

The US Government Accountability Office (GAO) recently stated that the King Stallion’s planned entry into low-rate production has been delayed eight months to February 2017 because of technical difficulties.

The aircraft is being developed for the US Marine Corps to replace the heavy-lift CH-53E, and should be ready for duty in 2019.

Although the US government bears the ultimate cost of delays and overruns, NAVAIR says schedule incentives were part of the arrangement “and Sikorsky was impacted due to schedule slides”.

The latest development cost estimate stands at $6.8 billion, $2 billion more than originally imagined.

Asset Image

Sikorsky/Lockheed Martin

The super-heavy-lift helicopter’s two critical technologies are the split torque gearbox and seven anhedral swept-tip composite main rotor blades and both are now flying on the first two engineering design model (EDM) aircraft. However, problems reported with the main gear box did set back the overall test schedule by delaying first flight.

“The redesigned components are flying in the test aircraft and are performing well,” confirms NAVAIR in an email to Flightglobal. “The redesigned components are flying in both test assets currently flying, and no further changes are anticipated. There has been no impact to the flight schedule because the changes were made prior to first flight.”

The programme has also been working with unnamed suppliers to “find efficiencies” and all redesigned components were ground testing prior to retrofit and flight on EDM-1. NAVAIR expects the third and fourth aircraft to join the test campaign “before the end of summer 2016”.





Recommended

Kaszek makes first aviation AI investment, backing TravelX's trillion-dollar dynamic inventory vision

TravelX announced that Kaszek, Latin America's leading venture capital firm, made a substantial investment in its platform, bringing the company's total funding to $45 million. The invest...

FL Technics adds 4 new aircraft approvals in UAE expanding wide-body portfolio

FL Technics subsidiary FL Technics LLC, which provides Line Maintenance services across the Middle East, has expanded its approved capabilities by adding Airbus A350, Boeing 777, Boeing 787, and Boein...

Do228 NXT makes its African debut at El Alamein Airshow in Egypt and AAD 2026 in South Africa

In September 2026, General Atomics AeroTec Systems will put a major focus on Africa. With two trade show appearances, the German aircraft manufacturer is highlighting the strategic importance of...

FAI strengthens long-range charter fleet with second Global 6000 in a year

FAI rent-a-jet has further strengthened its fleet with the addition of a Bombardier Global 6000 (D-AFAN, MSN 9471). The acquisition was completed just five weeks after the LOI was signed, underli...

Android Apps development in Riga, Latvia