Sikorsky CH-53K programme puts gearbox issues behind it

Download: Printable PDF Date: 13 Apr 2016 04:05 (UTC) category:
Publisher:
Sikorsky CH-53K programme puts gearbox issues behind it - Manufacturer publisher
Tatjana Obrazcova
Country: United States Aircraft: Helicopters
Source: Flightglobal

US Naval Air Systems Command (NAVAIR) appears to be confident that the Sikorsky CH-53K programme has put the gearbox failures and parts delays experienced prior to first flight in October 2015 behind it, but the Lockheed Martin-owned helicopter manufacturer won’t receive bonus cheques for lateness.

The US Government Accountability Office (GAO) recently stated that the King Stallion’s planned entry into low-rate production has been delayed eight months to February 2017 because of technical difficulties.

The aircraft is being developed for the US Marine Corps to replace the heavy-lift CH-53E, and should be ready for duty in 2019.

Although the US government bears the ultimate cost of delays and overruns, NAVAIR says schedule incentives were part of the arrangement “and Sikorsky was impacted due to schedule slides”.

The latest development cost estimate stands at $6.8 billion, $2 billion more than originally imagined.

Asset Image

Sikorsky/Lockheed Martin

The super-heavy-lift helicopter’s two critical technologies are the split torque gearbox and seven anhedral swept-tip composite main rotor blades and both are now flying on the first two engineering design model (EDM) aircraft. However, problems reported with the main gear box did set back the overall test schedule by delaying first flight.

“The redesigned components are flying in the test aircraft and are performing well,” confirms NAVAIR in an email to Flightglobal. “The redesigned components are flying in both test assets currently flying, and no further changes are anticipated. There has been no impact to the flight schedule because the changes were made prior to first flight.”

The programme has also been working with unnamed suppliers to “find efficiencies” and all redesigned components were ground testing prior to retrofit and flight on EDM-1. NAVAIR expects the third and fourth aircraft to join the test campaign “before the end of summer 2016”.





Recommended

Airbus A350F freighter successfully performs its maiden flight

The Airbus A350F freighter (MSN 700), the first of two flight test aircraft, has successfully completed its maiden flight. Equipped with dedicated flight test instrumentation, the aircraft spent 4 hou...

SkyDrive eyes Osaka’s rooftops for a new generation of eVTOL vertiports

Following the successful public flight demonstrations at Expo 2025 Osaka, SkyDrive announced plans to undertake a feasibility study exploring the conversion of Osaka City’s existi...

TFC Flight Traininge elevates pilot training journey with new Pipistrel Explorer

TFC Flight Training has become the first flight school in Germany to operate the Pipistrel Explorer following the delivery of two aircraft from Pipistrel, a Textron Inc. company and affiliate of Textr...

ATP Flight School hosts Alumni Career Expo featuring 20 airline and industry partners

On October 1, ATP Flight School will welcome nearly 500 aspiring airline pilots to its Arlington, Texas training center for an exclusive career expo featuring 20 airline and industry partners. Attende...

Android Apps development in Riga, Latvia